Forum Discussion
Robert0842
May 10, 2021Tin Contributor
Task ID and Predecessor with VBA
Hi, In a mpp file I have the tasks ID and predecessors of many tasks. I need to transmit them into another mpp file using VBA. The tasks are not listed in the same order. How can I do that ? Thank...
Robert0842
May 11, 2021Tin Contributor
Hi,
Thanks for trying to help me.
I'll try to explain more accurately.
The user created a schedule: 1600 tasks and a WBS, and then he activated a grouping.
Now he wants the structure of the grouping as a new WBS.
The Copy and Paste works fine for most of the fields, but it doesn't work for the Predecessors column. For example, in the original file the predecessor of Task 3 was Task 2, but in the new file Task ID 2 is its own summary.
Any idea?
Thanks again
Thanks for trying to help me.
I'll try to explain more accurately.
The user created a schedule: 1600 tasks and a WBS, and then he activated a grouping.
Now he wants the structure of the grouping as a new WBS.
The Copy and Paste works fine for most of the fields, but it doesn't work for the Predecessors column. For example, in the original file the predecessor of Task 3 was Task 2, but in the new file Task ID 2 is its own summary.
Any idea?
Thanks again
Miles_Goodchild
May 12, 2021Brass Contributor
The real issue may arise if your user has linked to or from Summary Lines - I would remove these before attempting to run the group and re-order as per Dale's comment. There will be some manual work to build the new WBS and structure however this will not be a massive task and will be a lot less than messing around with VBA I suspect 🙂