Task Finish Date Not Updating Based on Finish To Finish Predecessor

I have a "Project Management" task that spans the duration of the project to account for my Project management work.  I created added the last task in the project as a predecessor to my Project Manag...
  • John-project's avatar
    Sep 02, 2022

    JBLT-77 

    You can't get there from here with a finish-to-finish link. My guess is that you recorded actuals against the project management task (e.g. actual start). That locked in the span of the management task so the finish-to-finish link with the newly updated project complete task was effectively nulled.

     

    What you should have done (do) is use a hammock task as your project managment task. It will expand/contract to meet the changes in the plan. I thought this was mentioned in one of your many previous posts but maybe not. At any rate, see this Wiki article:
    https://social.technet.microsoft.com/wiki/contents/articles/32040.ms-project-hammock-tasks.aspx 
    John