Task duration vs completion date
Thanks John-project. I think I understand what you are saying. Do you have an example image of what this looks like?
Sure. Project has three task types, fixed work, fixed units (i.e. resources), and fixed duration. Project's scheduling engine uses the following equation:
Duration = Work/Units
The default task type is fixed work, so the number of units (resources) assigned drives the duration. With a fixed duration task, the time span (duration) is fixed and amount of work and resources are the variables.
Based on your example, the duration is set at 60 days and the work is set at 80h (assuming a normal 8/5 workweek). With those inputs, the single resource's assignment will be 17% of a normal full time employee. Project will automatically spread the 80 hours of work linearly over the full time span as shown in the lower pane (Task Usage view). Work hours can be manually edited within the full duration a selection of Work Contour's can be selected for the assignment (default contour is Flat).
Hope this helps.
John