Table for the timeline in MS Project
- Jan 06, 2023
Hello shzlinn ,
Unfortunately this data is not surfaced in the reporting API for Project Online. You could do this manually with an enterprise custom task field but that would need the owners of the projects to keep that field value updated each time they add or remove a task to the timeline. Then this data will be available in the Task endpoint in the reporting API after the projects are published.
Paul
Hello shzlinn ,
Unfortunately this data is not surfaced in the reporting API for Project Online. You could do this manually with an enterprise custom task field but that would need the owners of the projects to keep that field value updated each time they add or remove a task to the timeline. Then this data will be available in the Task endpoint in the reporting API after the projects are published.
Paul
Paul_Mather Thank you for the info. I thought so.