Table for the timeline in MS Project

Hello,  We have created manual timelines for all our projects in MS Project App (the timeline that appears on top of the Gantt Chart).  I am wondering if this data is stored in any database table (...
  • Paul_Mather's avatar
    Jan 06, 2023

    Hello shzlinn ,

    Unfortunately this data is not surfaced in the reporting API for Project Online. You could do this manually with an enterprise custom task field but that would need the owners of the projects to keep that field value updated each time they add or remove a task to the timeline. Then this data will be available in the Task endpoint in the reporting API after the projects are published.

    Paul