SV Negative value But Status On Schedule?

Hi   Can someone help explain why my SV value is negative which I understand means my project is behind schedule based on earn value analysis but my project status is showing on schedule? Is there ...
  • PlannersPlace's avatar
    Dec 30, 2022

    KR 

     

    Earn Value Analysis makes use of Baseline data while the "Status" field has nothing to do with Baseline. The "Status" field is based on the following fields

    • Start Date
    • % Complete
    • Status Date

    E.g. If "Status Date" is Day 5 and a 10-day Task is shown as 50% complete on Day 5, then "Status" field value is "On Schedule" but if this 10-day Task is shown as 20% on Day 5, then "Status" field value is "Late".

     

    A Task that is 100% complete will have "Status" field value as "Complete" while a Task whose "Start Date" is greater than "Status Date" will have "Status" field value of "Future Task".

     

    =jerome