Forum Discussion
SV Negative value But Status On Schedule?
- Dec 30, 2022
Earn Value Analysis makes use of Baseline data while the "Status" field has nothing to do with Baseline. The "Status" field is based on the following fields
- Start Date
- % Complete
- Status Date
E.g. If "Status Date" is Day 5 and a 10-day Task is shown as 50% complete on Day 5, then "Status" field value is "On Schedule" but if this 10-day Task is shown as 20% on Day 5, then "Status" field value is "Late".
A Task that is 100% complete will have "Status" field value as "Complete" while a Task whose "Start Date" is greater than "Status Date" will have "Status" field value of "Future Task".
=jerome
Earn Value Analysis makes use of Baseline data while the "Status" field has nothing to do with Baseline. The "Status" field is based on the following fields
- Start Date
- % Complete
- Status Date
E.g. If "Status Date" is Day 5 and a 10-day Task is shown as 50% complete on Day 5, then "Status" field value is "On Schedule" but if this 10-day Task is shown as 20% on Day 5, then "Status" field value is "Late".
A Task that is 100% complete will have "Status" field value as "Complete" while a Task whose "Start Date" is greater than "Status Date" will have "Status" field value of "Future Task".
=jerome
- KRDec 30, 2022Copper ContributorHi
Thanks for the prompt reply and providing the clarification. Your rseponse much appreciated.
Best Rgds
Kish