Summary task doesn't consider sub task dates
Hi folks - I am new to MS project and am struggling with the metadata on summary tasks. You can see in this image I have an 'Initiate Project' summary task which consists of several sub-tasks. When I...
- Sep 06, 2019
Hello Kateraid
This is because your tasks are manually scheduled in your example and those tasks do not have any duration. Either add duration to the manually scheduled tasks or switch to auto scheduled tasks like in the example below:
Hope that helps
Paul
Paul_Mather
Sep 06, 2019MVP
Hello Kateraid
This is because your tasks are manually scheduled in your example and those tasks do not have any duration. Either add duration to the manually scheduled tasks or switch to auto scheduled tasks like in the example below:
Hope that helps
Paul