Summarize by Rollup Task and Resource Group

Is there a way to write a report that groups resource groups under top level task and rolls up the summary values? Specifically:

 

  • List all level two tasks
  • Under each level 2 task, list the resource groups working on any task in that group
  • Values SUM(Cost) and SUM(Actual Cost)

 

The output would look something like this:

 

L2 Task A

   - R Group X [##] [##]

   - R Group Y [##] [##]

L2 Task B

   - R Group Y [##] [##]

   - R Group Z [##] [##]

 

I've been able to group by Resource Group and by L2 Tasks but not both.

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor

    rwl01,

    You mean something like this? (grouped on Resource Usage view)

    To do it create a custom field

    Text1="L2 - " & [Name]

    Then group by Text1 (task) and then by Resource Group (assignment) and select the option to "group assignments, not tasks"

     

    John