Forum Discussion

marce1656's avatar
marce1656
Copper Contributor
Jan 22, 2022
Solved

Status ms project

why does a status of a task show up as on schedule when i haven't put in a start or finish date in ms project

  • marce1656,
    But that's the reason for using Project. If you think you already know all the dates, why not just put everything in a spreadsheet in Excel?

    The correct way to use (and get the benefit from) Project is to first enter all the activities (tasks) required to accomplish your end goal (i.e. a product or service). Second, enter the estimated time span for each activity into the Duration field. Note, the duration is NOT the amount of work required to complete the task but the time span to complete the task. Third, connect the tasks in a logical sequence of performance via the Predecessor field. Most links will be finish-to-start but other variations might also be appropriate. (start-to-start, finish-to-finish, lead, lag). Given those entries, Project calculates all task start and finish dates (and times) based on the Project calendar. If the resulting plan doesn't meet the desired end date, then adjust tasks, durations and/or task links. After that is done, assign resources to each of the tasks. Most likely that will change the plan such that further adjustment is needed.

    John

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    marce1656,
    Please explain what you mean by "status of a task".

    Also, unless you are using manual scheduling, you should NOT be entering start and/or finish dates for tasks. And if you want a good plan that responds to dynamic changes, (i.e. the real world), you shouldn't be using manual scheduling either.
    John
    • marce1656's avatar
      marce1656
      Copper Contributor
      But if i use automatic scheduling when i enter a task it generates a start and finish date on its own. Generally when i start a schedule I type in all the tasks and then i generate start and finish dates.
      • John-project's avatar
        John-project
        Silver Contributor
        marce1656,
        But that's the reason for using Project. If you think you already know all the dates, why not just put everything in a spreadsheet in Excel?

        The correct way to use (and get the benefit from) Project is to first enter all the activities (tasks) required to accomplish your end goal (i.e. a product or service). Second, enter the estimated time span for each activity into the Duration field. Note, the duration is NOT the amount of work required to complete the task but the time span to complete the task. Third, connect the tasks in a logical sequence of performance via the Predecessor field. Most links will be finish-to-start but other variations might also be appropriate. (start-to-start, finish-to-finish, lead, lag). Given those entries, Project calculates all task start and finish dates (and times) based on the Project calendar. If the resulting plan doesn't meet the desired end date, then adjust tasks, durations and/or task links. After that is done, assign resources to each of the tasks. Most likely that will change the plan such that further adjustment is needed.

        John