Status indicators disappear after every check-in
- Apr 19, 2024
Thanks for your reply, and sorry for lack of precision about this:
I open the project from project center in the desktop app. It is checked-out to me when I add the indicators, and I always publish then close it and check it in.
The indicators are gone the next time I open the project in the desktop app (checked-out as well).
I treid a few things and came to the root cause:
All tasks don't have deadline. As a consequence Date3 is mostly empty, displaying "NC". In these cells I want no indicator at all, just a blank space; I added the rule as shown in attachment:
If Date3 equals NC then no indicator is displayed.
Apparently it's this test that stops my indicators from being saved. If I remove this test, the red and green indicators are correctly saved next time I open my project.
However without this test, indicators will just display as green for every cell with "NC", which is pointless.
Does anyone have a workaround it? I don't understand why my rule cannot be saved while it works just fine.
Thanks.
Hello.
Can you confirm if the same thing happens with Date4, for example, if you add the Date4 column to the table, whose formula is Date4=Date3, including in Date4 the same graphical indicator rule as Date3, with Date3 being the deadline entry?
Ignacio
- KnoppGruntApr 18, 2024Copper Contributor
Hello and thanks for your suggestion,
The exact same thing happens with Date4.
I also tried to change the rule for NC: use an indicator (instead of nothing at all) and let it not be the 1st rule; as shown in attachment. Not anymore luck.Is there another way to "hide" all the NC value in Date3 field? I don't mind if I can achieve it another way.
Thanks.