Forum Discussion
Status indicators disappear after every check-in
- Apr 19, 2024
Thanks for your reply, and sorry for lack of precision about this:
I open the project from project center in the desktop app. It is checked-out to me when I add the indicators, and I always publish then close it and check it in.
The indicators are gone the next time I open the project in the desktop app (checked-out as well).
I treid a few things and came to the root cause:
All tasks don't have deadline. As a consequence Date3 is mostly empty, displaying "NC". In these cells I want no indicator at all, just a blank space; I added the rule as shown in attachment:
If Date3 equals NC then no indicator is displayed.
Apparently it's this test that stops my indicators from being saved. If I remove this test, the red and green indicators are correctly saved next time I open my project.
However without this test, indicators will just display as green for every cell with "NC", which is pointless.
Does anyone have a workaround it? I don't understand why my rule cannot be saved while it works just fine.
Thanks.
- Ignacio_MartinApr 18, 2024Steel Contributor
Hello.
Can you confirm if the same thing happens with Date4, for example, if you add the Date4 column to the table, whose formula is Date4=Date3, including in Date4 the same graphical indicator rule as Date3, with Date3 being the deadline entry?
Ignacio
- KnoppGruntApr 18, 2024Copper Contributor
Hello and thanks for your suggestion,
The exact same thing happens with Date4.
I also tried to change the rule for NC: use an indicator (instead of nothing at all) and let it not be the 1st rule; as shown in attachment. Not anymore luck.Is there another way to "hide" all the NC value in Date3 field? I don't mind if I can achieve it another way.
Thanks.