Forum Discussion

AurelioDM's avatar
AurelioDM
Copper Contributor
Mar 28, 2023
Solved

Start task when predecessor is complete

Good afternoon all   I created a project in Project and exported it into the Web App.  But one thing is very unclear to me. When I set the path for the tasks, I expected that the task was blocked ...
  • John-project's avatar
    Mar 28, 2023
    AurelioDM,
    The "solution" is understanding that Project will allow users to do things that don't necessarily make sense. So, yes, a successor task can show progress, even completion, regardless of whether the predecessor task is complete. In reality it just might be that the task dependency was not firm and the successor task could start before the predecessor was complete. It's not that uncommon.

    Hope this helps.
    John

Resources