Forum Discussion

GiuseppePalaia's avatar
GiuseppePalaia
Copper Contributor
Mar 28, 2024
Solved

Start successor when predecessor is not complete

Hi,   I have created a project, and I would like to link two tasks, namely Task1 and Task2, via the finish-to-start relationship.  Task1 lasts 10 months; Task2 lasts 5 months and starts when Task1...
  • malshayeb's avatar
    malshayeb
    Mar 28, 2024

    GiuseppePalaia 

     

    In this scenario i wouldn't use the split task feature but i would breakdown the work. I would breakdown Task 1 to (Task1 six months , Task2 four months) and create a relationship between them , then i add task 3 which is the five months one and link it to task one. in this scenario Task 3 will only be impacted if there was delay in the first 6 months and its unrelated to the second stretch of the work 

     

     

     

Resources