Sprint Weeks in Project

Hi - My challenge is to have the Project Sprints updated if the task start date moves. I have added Sprint weeks (to and from) in the Sprint Table. However it doesnt seem to update/change dynamically...
  • PlannersPlace's avatar
    Oct 12, 2022

    LouC123 

     

    Try this formula

     

    IIf([Number1]>"44850" And [Number1]<"44886","sprint10", IIf([Number1]>"44885" And [Number1]<"44920","sprint11","unknown"))

     

    This is a nested IIF

    1. The first blue part is your test criteria for sprint 10 and if it is true, it returns the first green part
    2. But if it is false, we then test for sprint 11, which is the second blue part and if it is true, it returns the second green part
    3. If test for sprint 11 is also false, then we return unknown, which is the red part.

    =jerome