Forum Discussion
Sprint Weeks in Project
- Oct 12, 2022
Try this formula
IIf([Number1]>"44850" And [Number1]<"44886","sprint10", IIf([Number1]>"44885" And [Number1]<"44920","sprint11","unknown"))
This is a nested IIF
- The first blue part is your test criteria for sprint 10 and if it is true, it returns the first green part
- But if it is false, we then test for sprint 11, which is the second blue part and if it is true, it returns the second green part
- If test for sprint 11 is also false, then we return unknown, which is the red part.
=jerome
Try this formula
IIf([Number1]>"44850" And [Number1]<"44886","sprint10", IIf([Number1]>"44885" And [Number1]<"44920","sprint11","unknown"))
This is a nested IIF
- The first blue part is your test criteria for sprint 10 and if it is true, it returns the first green part
- But if it is false, we then test for sprint 11, which is the second blue part and if it is true, it returns the second green part
- If test for sprint 11 is also false, then we return unknown, which is the red part.
=jerome
- LouC123Oct 12, 2022Copper Contributor
Well, what can I say...thanks - works treat 🙂
I had to add the rest of the sprints:
IIf([Number1]>"44850" And [Number1]<"44884","sprint10",
IIf([Number1]>"44885" And [Number1]<"44919","sprint11",
IIf([Number1]>"44920" And [Number1]<"44933","Xmas",
IIf([Number1]>"44934" And [Number1]<"44968","sprint12",
IIf([Number1]>"44969" And [Number1]<"45003","sprint13",
IIf([Number1]>"45004" And [Number1]<"45038","sprint14",
IIf([Number1]>"45039" And [Number1]<"45066","sit1",
IIf([Number1]>"45067" And [Number1]<"45094","sit2",
IIf([Number1]>"45095" And [Number1]<"45116","UAT1",
IIf([Number1]>"45116" And [Number1]<"45129","UAT2",
IIf([Number1]>"451310" And [Number1]<"45157","Go-live","unknown")))))))))))Thanks again - dynamically updates too !!