Spreading out work over a date range in MS Project?
Hey all, I'm a new Project user currently building an IMS. Several tasks in the schedule take a certain number of hours (i.e. 40 hours) but the date range has been stated by the managers to be 2 week...
- Aug 15, 2023
Yes. Make the tasks of fixed duration type. That will "lock" the start and finish and allow work hours to be spread over that period or manually edited as desired. This is what it might look like in the Task Usage view, but you can edit daily work hours if needed,
John
nrmiller
Sep 12, 2023Copper Contributor
Thank you so much!!
John-project
Sep 12, 2023Silver Contributor
nrmiller,
You're welcome and thanks for the feedback.
John
You're welcome and thanks for the feedback.
John