Spreading out work over a date range in MS Project?

Hey all, I'm a new Project user currently building an IMS. Several tasks in the schedule take a certain number of hours (i.e. 40 hours) but the date range has been stated by the managers to be 2 week...
  • John-project's avatar
    Aug 15, 2023

    nrmiller 

    Yes. Make the tasks of fixed duration type. That will "lock" the start and finish and allow work hours to be spread over that period or manually edited as desired. This is what it might look like in the Task Usage view, but you can edit daily work hours if needed,