Hello Zhipa ,
The only out of the box solution is to Link a task in Microsoft Project to a Planner plan as seen here: https://pwmather.wordpress.com/2017/08/29/link-projectonline-tasks-to-planner-microsoft365-ppm-pmot-msproject/
There are 3rd party solutions to sync Project Online and Planner, I've not used any so can't recommend any but here is an example:
https://fluentpro.com/microsoft-project-online-office-365-planner/
Paul
Hello Zhipa ,
The only out of the box solution is to Link a task in Microsoft Project to a Planner plan as seen here: https://pwmather.wordpress.com/2017/08/29/link-projectonline-tasks-to-planner-microsoft365-ppm-pmot-msproject/
There are 3rd party solutions to sync Project Online and Planner, I've not used any so can't recommend any but here is an example:
https://fluentpro.com/microsoft-project-online-office-365-planner/
Paul
- ZhipaJun 03, 2022Copper Contributor
Fabulous Paul_Mather
Thank you for your message and I will analyze the articles that you indicate.
Thanks for sharing.