Show Sprints on Gantt Chart
Hello, I use MS Project Desktop. I have activated agile features (each task is in a sprint). Still, I find that the Gantt view is useful. Can't we show sprints in the gantt view? For example, h...
RatanPushp
Jul 13, 2023Brass Contributor
With the use of Group by "Sprint" option in View tab, the sprint task will be visible in Gantt Chart.
Whereas, to highlight sprint week period in Gantt Chart, modify the bar style of "Group by Summary" with Sprint Start and Sprint Finish (in From and To columns) and also select color or pattern as per your preference.
I hope this helps you.