Forum Discussion
NKumar2010
May 22, 2022Brass Contributor
Show Dependency without Changing Timelines
Hi, I have three tasks, let's call it Task A, B and C. Task A is predecessor (FS relation) of Task C. So task C's start date is dictated by Task A finish date. Task B is not a predecesso...
- May 23, 2022NKumar2010 --
No, what you want to do is not possible. I would recommend you link Task A and Task C with an FS dependency, and then link Task B and Task C with an FS dependency as well. Hope this helps.
May 23, 2022
NKumar2010 --
No, what you want to do is not possible. I would recommend you link Task A and Task C with an FS dependency, and then link Task B and Task C with an FS dependency as well. Hope this helps.
No, what you want to do is not possible. I would recommend you link Task A and Task C with an FS dependency, and then link Task B and Task C with an FS dependency as well. Hope this helps.
NKumar2010
May 23, 2022Brass Contributor
Thanks Dale.