Forum Discussion
Reuben
Jan 06, 2022Iron Contributor
'Show all subtasks' does not expand all the subtasks for all the sub projects
When I click 'Show all subtasks' in my Master project it does not expand all the subtasks for all the sub projects. Only some of the sub projects expand. If I click in on one of the collapsed tasks...
- Jan 06, 2022Reuben --
No idea why that is happening. I have not encountered this personally. Out of curiosity, what happens if you click the Select All button, and then click Outline > Show all subtasks? Does that work? If so, that is your workaround to this problem. Hope this helps.
Jan 06, 2022
Reuben --
No idea why that is happening. I have not encountered this personally. Out of curiosity, what happens if you click the Select All button, and then click Outline > Show all subtasks? Does that work? If so, that is your workaround to this problem. Hope this helps.
No idea why that is happening. I have not encountered this personally. Out of curiosity, what happens if you click the Select All button, and then click Outline > Show all subtasks? Does that work? If so, that is your workaround to this problem. Hope this helps.
- ReubenJan 06, 2022Iron ContributorHa! That worked!
Nice workaround. Thanks Dale.- Jan 07, 2022Reuben --
You are more than welcome for the help, my friend. Since my reply answered your question, would you please mark my previous reply as the answer? Thanks!