Show a gantt chart over a weekend in MS Project...
Hi team I can see a gantt chart if someone works on Monday to Sat or Sun to Friday. However on a standard calendar, I want to show 2 days work starting Friday and finishing Monday. However the gan...
- Jan 25, 2022Jamesp435,
Yes and no. If your project calendar is customized to have a non-standard workweek, then you can set the Timescale display to show Gantt bars that show work per the custom calendar. But if the custom calendar only applies to selected tasks, then Project limits the Gantt Timescale display to only show one calendar's workweek. The option is set via double clicking on the timescale to bring up the Timescale window and clicking on the "Non-working time" tab. Set the appropriate calendar.
Note, for a normal Standard calendar display you can also set the option to show non-working time in front of Gantt Bars. That addresses the issue of Gantt Bars appearing as "active" during non-working time.
Hope this helps.
Jonn
Jamesp435
Jan 31, 2022Brass Contributor
Nice one. Thanks John
John-project
Feb 01, 2022Silver Contributor
Jamesp435,
You're welcome and thanks for the feedback.
John
You're welcome and thanks for the feedback.
John