Sharepoint tasks and Project WPA synchronization
Hello, I started using sharepoint tasks list to manage different projects of my company ( each project with a list like: https://contoso.sharepoint.com/sites/CompanyProjectSite/Lists/Tasks/AllItems.a...
Paul_Mather
Oct 22, 2021MVP
Hello RobertoPangallo ,
You can Add SharePoint Sites in PWA using the Site that contains a task list:
Here is a blog post that covers this (it's a very old post but the process is still the same):
Paul
RobertoPangallo
Oct 22, 2021Copper Contributor
Thanks Paul_Mather!
I meant synchronization between lists already created in the Office 365 Sharepoint collection "..../sites/.../" and the PWA ones "../sites/PWA/...".
In PWA, if I use the function "Add Sharepoint Sites", it will only search in the "../sites/PWA/..." collection, not in the "..../sites/.../"...
- Paul_MatherOct 22, 2021MVP
Hello RobertoPangallo ,
PWA can only include Task Lists from sites within the PWA site collection. It will not be able to access Task lists on sites in other site collections.
Paul