Shared resources issue
Hello, I'm facing an issue with shared resources: I have 2 project files (A.mpp & B.mpp) using shared resources in C.mpp I got rid of B.mpp, but shared resources show as taken by B.mpp I ...
Feb 13, 2023
MarkDury --
Open the shared resource pool file Read/Write. Click Resource > Resource Pool > Share Resources. You should see a dialog that looks similar to the one below. Select Project B in this dialog and then click the Break Link button. Close the dialog and save the shared resource pool file. Hope this helps.
MarkDury
Feb 13, 2023Copper Contributor
Thanks you so much Dale, that really helped
- Feb 13, 2023Mark --
You are more than welcome for the help, my friend! 🙂