Forum Discussion
MarkDury
Feb 13, 2023Copper Contributor
Shared resources issue
Hello, I'm facing an issue with shared resources: I have 2 project files (A.mpp & B.mpp) using shared resources in C.mpp I got rid of B.mpp, but shared resources show as taken by B.mpp I ...
Feb 13, 2023
MarkDury --
Open the shared resource pool file Read/Write. Click Resource > Resource Pool > Share Resources. You should see a dialog that looks similar to the one below. Select Project B in this dialog and then click the Break Link button. Close the dialog and save the shared resource pool file. Hope this helps.
- MarkDuryFeb 13, 2023Copper ContributorThanks you so much Dale, that really helped
- Feb 13, 2023Mark --
You are more than welcome for the help, my friend! 🙂