Setting a default calendar for all new projects
I want to set up my Project 2019 so that every time I open a new blank project it defaults to a particular calendar that I have created. Can this be done, or do you have to open a new blank project a...
- Jun 07, 2024
Hi Glen.
1. Modify the Standard calendar of any mpp project with your custom data and keep it open in memory.
2. Copy and replace the modified Standard calendar from the open mpp file to the Global.mpt file, through the Calendar tab of the Organizer, in Menu > Info > Organizer .
From that moment on, new projects will be assigned to your standard calendar by default.
I hope I've helped.
Ignacio
GlenF1960
Jun 12, 2024Copper Contributor
I so appreciate the responses from both of you, so Thanks for that!
In the end, I think John made a good point and decided against what I had planned on doing, which was described well by Ignacio. I added the Calendar I created to the Global templates with a different name than "Standard", and I will just select it for each new project.
Thanks again to both of you.
In the end, I think John made a good point and decided against what I had planned on doing, which was described well by Ignacio. I added the Calendar I created to the Global templates with a different name than "Standard", and I will just select it for each new project.
Thanks again to both of you.
- John-projectJun 12, 2024Silver Contributor