Setting a default calendar for all new projects
- Jun 07, 2024
Hi Glen.
1. Modify the Standard calendar of any mpp project with your custom data and keep it open in memory.
2. Copy and replace the modified Standard calendar from the open mpp file to the Global.mpt file, through the Calendar tab of the Organizer, in Menu > Info > Organizer .
From that moment on, new projects will be assigned to your standard calendar by default.
I hope I've helped.
Ignacio