Forum Discussion
Set weekends as Working Days in MS Project
How can I set weekends (Saturday and Sunday off) as working days in MS Project? I have gone to Project -> Change working hours and clicked on Working week. However, I cannot click on the “Details” button. Can someone please help me?
2 Replies
Rumi --
Is your organization using either Project Online or Project Server with Microsoft Project? If the answer is Yes, then you cannot create new calendars or edit existing calendard directly in Microsoft Project, which would explain why the Details button is grayed out. You need to start the creating or editing process in Project Web App instead, which will then take you to the Change Working Time dialog in Microsoft Project, with the creation and editing features enabled. Let us know and we will try to help you.
- Ignacio_MartinSteel Contributor
Rumi
Do you have the row selected and it is in gray background color?
Ignacio