Set a unique schedule for a specific resource (Project for the Web)
Hi all,
I try to use the Resource Calendars in Project for the web
What I did is:
1/ Create the Generic resource, which works from 9am - 5pm, from Monday - Friday
2/ Set up a calendar template for all project base on Generic user working hour
3/ Create a project with the calendar template I just created
4/ Prepare a user (resource)
5/ Set up working hours for this user (9AM - 1PM, from Monday - Friday)
6/ Create some dummy task
+ Task 1: duration 1 day, start from 1/1/2020, end at 1/1/2020
+ Task 2: duration 2 days, start from 1/1/2020, end at 1/2/2020
+ Task 3: duration 4 hours, start from 1/1/2020, end at 1/1/2020
+ Task 4: duration 8 hours, start from 1/1/2020, end at 1/1/2020
7/ Try to assign the user to those tasks
Those tasks's end dates stay the same, ignoring the user's working hours
=>>> I expect those tasks's end dates should follow the user's working hours => Any advice?