Forum Discussion

cuonglt0105's avatar
cuonglt0105
Copper Contributor
Jun 12, 2023

Set a unique schedule for a specific resource (Project for the Web)

Hi all,

 

I try to use the Resource Calendars in Project for the web

What I did is:

1/ Create the Generic resource, which works from 9am - 5pm, from Monday - Friday

Tạo generic user

2/ Set up a calendar template for all project base on Generic user working hour

set up calendar template

3/ Create a project with the calendar template I just created

Tạo project

4/ Prepare a user (resource)

5/ Set up working hours for this user (9AM - 1PM, from Monday - Friday)

6/ Create some dummy task

+ Task 1: duration 1 day, start from 1/1/2020, end at 1/1/2020

+ Task 2: duration 2 days, start from 1/1/2020, end at 1/2/2020

+ Task 3: duration 4 hours, start from 1/1/2020, end at 1/1/2020

+ Task 4: duration 8 hours, start from 1/1/2020, end at 1/1/2020

7/ Try to assign the user to those tasks

Those tasks's end dates stay the same, ignoring the user's working hours

 

=>>> I expect those tasks's end dates should follow the user's working hours => Any advice?

No RepliesBe the first to reply

Resources