Selectively Removing Dependency arrows (but not the dependency itself)
Is there a way in Project to selectively hide dependency arrows? I know I can hide them globally, but there are times when I'd like to still have a dependency impacting a certain task, but not have ...
Gordon_Smith
Sep 21, 2022Tin Contributor
Could I selectively color some of them white?
Sep 21, 2022
Gordon --
Good idea. I thought of that when I was writing my original reply. The problem is that the link line inherits its color from the color of the predecessor's Gantt bar. If the Gantt bar is blue, the link line is blue. If the Gantt bar is red, the link line is red. If you make the Gantt bar white, the Gantt bar disappears, and the link line is gray (go figure).
So, no, you cannot selectively color some of them white. Sorry, but good try.
Good idea. I thought of that when I was writing my original reply. The problem is that the link line inherits its color from the color of the predecessor's Gantt bar. If the Gantt bar is blue, the link line is blue. If the Gantt bar is red, the link line is red. If you make the Gantt bar white, the Gantt bar disappears, and the link line is gray (go figure).
So, no, you cannot selectively color some of them white. Sorry, but good try.