Forum Discussion
Gordon_Smith
Sep 21, 2022Tin Contributor
Selectively Removing Dependency arrows (but not the dependency itself)
Is there a way in Project to selectively hide dependency arrows? I know I can hide them globally, but there are times when I'd like to still have a dependency impacting a certain task, but not have ...
Sep 21, 2022
Gordon --
Unless I am sadly mistaken, hiding the link lines is an "all or nothing" process. In the Layout dialog, you can hide all of them or you can display all of them, but there is no way to selectively hide the link lines in a project. Sorry, but hope this helps.
Unless I am sadly mistaken, hiding the link lines is an "all or nothing" process. In the Layout dialog, you can hide all of them or you can display all of them, but there is no way to selectively hide the link lines in a project. Sorry, but hope this helps.
- Gordon_SmithSep 21, 2022Tin ContributorCould I selectively color some of them white?
- Sep 21, 2022Gordon --
Good idea. I thought of that when I was writing my original reply. The problem is that the link line inherits its color from the color of the predecessor's Gantt bar. If the Gantt bar is blue, the link line is blue. If the Gantt bar is red, the link line is red. If you make the Gantt bar white, the Gantt bar disappears, and the link line is gray (go figure).
So, no, you cannot selectively color some of them white. Sorry, but good try.