Forum Discussion

GKE2019's avatar
GKE2019
Brass Contributor
Nov 28, 2022

Scheduled hours

Is it possible that you can assign person x for 40hours a week, and person z for 32 hours a week?

1 Reply

  • GKE2019 --

    The only way this is possible is if the calendar for the first resource shows that the resource works 40h per week and the calendar for the second resource shows that the resource works 32h per week. Hope this helps.