Schedule Report
Is a view/report similar to this possible in MS Project? our plant is used to seeing an Excel spreadsheet like this, which is very efficient. Basically, it's a Gantt chart where each cell is a task...
- Jun 08, 2022RobertOrnelas,
Yeah Project has a lot of subtle options that can make all the difference.
1. Double click on the summary line to bring up the task information window. Check the "Hide Bar" option. That will hide the summary line bar but allow rolled up subtask bars to appear, as long as the Rollup field is marked ad "yes" for the summary and all subtasks.
2. There is no "Subtask Name" field, the field is simply "Name", as shown in my screenshot.
Does that help?
John
John-project
Jun 07, 2022Silver Contributor
Robert Ornelas,
I tend to agree with Dale. If Excel is the "cat's meow" for your organization why do you want to use Project?
However, if you do want to use Project, I'd say the Task Usage view, perhaps filtered or grouped, comes closest to the Excel spreadsheet format in your screen shot.
John
I tend to agree with Dale. If Excel is the "cat's meow" for your organization why do you want to use Project?
However, if you do want to use Project, I'd say the Task Usage view, perhaps filtered or grouped, comes closest to the Excel spreadsheet format in your screen shot.
John