Roadmap Group Sharing
I'm using https://project.microsoft.com and Roadmap. I have created a new roadmap for my project in Roadmap and on the top right > members I have shared this with a group. Now I want to revoke th...
- Apr 26, 2022Thanks for confirming Paul Mather
Seems like a real limitation of the spftware.
I was able to copy the project and start again.
Paul_Mather
Apr 26, 2022MVP
Hello jonboylib ,
It is not possible to remove the Group once you have selected it - this is documented here: https://support.microsoft.com/en-us/office/video-share-a-roadmap-with-a-group-d3ecd978-560d-41e3-b75f-7774386fb701
All you can do it is remove the users from the Group via the Microsoft 365 Groups UI.
Paul
jonboylib
Apr 26, 2022Iron Contributor
Thanks for confirming Paul Mather
Seems like a real limitation of the spftware.
I was able to copy the project and start again.
Seems like a real limitation of the spftware.
I was able to copy the project and start again.