Forum Discussion

CuriousProjectUser's avatar
CuriousProjectUser
Brass Contributor
Sep 02, 2022
Solved

Roadmap / User can't connect to own MS Project Online project / Invalid app connection for flow

Dear all,   we're having an issue with a roadmap where a user cannot connect to a project in MS Project Online where she is the owner. The project can be selected, but once she is about to confirm...
  • CuriousProjectUser's avatar
    Sep 14, 2022
    Clicking in the screenshot above on "add new connection" solved the issue. After re-entering the user-credentials connections to other projects could be added without any issue.

Resources