Risks and Issues in Project for the web?

Hi, I'm rolling out the new Project for my team and am trying to find out if there is functionality to document risks and issues within a project.  I know this feature was in earlier versions of Project, hoping it's still there. Thanks!!

3 Replies

  • Hi Kevin80,

    By default risks, issues and documents are not available in Project for the web. This capability does exist for Project Online / Project Server but not the latest Project app but.... you have several options to manage risks, issues and documents when using Project for the web. These include:

    • Once a project is linked to an Office 365 group, that Office 365 Group has a SharePoint site linked to it. You could create two new lists on that site for Risks and for Issues
    • Build a Model-driven Power App and add custom Risks / Issues entities to suit your requirements

    Paul