Forum Discussion
mhemolenaar
Dec 06, 2024Copper Contributor
Retrieve the original Project end-date
Good day! When creating a new project, I can choose the Project End date. Now, it's not uncommon that this date changes along the line. For instance, this change when one of the timelines changes in...
- Dec 09, 2024
mhemolenaar,
Yes, Project has always had a feature that preserves the original or interim snapshots of the plan and its called a baseline.
When a plan is first developed but just before starting execution, go to, Project > Schedule Group > Set Baseline. Project will capture several fields (Start, Finish, Cost, etc.) and store those in a set of Baseline fields. Those saved fields are then used as comparison between the original plan and the current schedule. They also form the basis for earned values metrics.
Hope this helps.
John
mhemolenaar
Dec 10, 2024Copper Contributor
Thank you John, this really helps!
Kind regards,
Maurice
John-project
Dec 10, 2024Silver Contributor
Maurice,
You're welcome and thanks for the feedback.
John