mhemolenaar,
Yes, Project has always had a feature that preserves the original or interim snapshots of the plan and its called a baseline.
When a plan is first developed but just before starting execution, go to, Project > Schedule Group > Set Baseline. Project will capture several fields (Start, Finish, Cost, etc.) and store those in a set of Baseline fields. Those saved fields are then used as comparison between the original plan and the current schedule. They also form the basis for earned values metrics.
Hope this helps.
John
mhemolenaar,
Yes, Project has always had a feature that preserves the original or interim snapshots of the plan and its called a baseline.
When a plan is first developed but just before starting execution, go to, Project > Schedule Group > Set Baseline. Project will capture several fields (Start, Finish, Cost, etc.) and store those in a set of Baseline fields. Those saved fields are then used as comparison between the original plan and the current schedule. They also form the basis for earned values metrics.
Hope this helps.
John
Thank you John, this really helps!
Kind regards,
Maurice
- John-projectDec 10, 2024Silver Contributor
Maurice,
You're welcome and thanks for the feedback.
John