Forum Discussion

Catalin_MS's avatar
Catalin_MS
Copper Contributor
Jun 06, 2023
Solved

Resources remaining availability in percentages

Hello, I`m trying to generate a MS Project Work Overview report, and in the Remaining availability Graphic on the Hours Scale I need in Percentages %, not in number of hours. (left side) Can anyone...
  • RodFromm's avatar
    Jun 06, 2023
    Based on my experience you cannot modify any of the Capacity Planning views, which is unfortunate. I created a set of custom power bi reports which allow me to display the data as needed.

Resources