Forum Discussion
Resources mapping using Project (Planner) and MS Power BI template
Hello Sidimm,
Resource utilization report is not part of Power BI report pack and require custom development. Assume, you are looking something similar to below report.
https://www.linkedin.com/posts/ratan-pushp_powerbi-projectonline-projectmanagement-activity-7295710080505630720-QDEV?utm_source=share&utm_medium=member_desktop&rcm=ACoAAARF1oIBYwYyPfvSAIEhai53QlcZqxpF6uk
I hope it is helpful for you!
Ratan Pushp
Hi Ratan,
This is exactly what I was looking for—thank you! Would you mind elaborating a bit on how you created it? and can it be built in the power BI dashboard.
Thanks again,
Sidi M
- RatanPushpAug 06, 2025Brass Contributor
Hello Sidi,
This resource utilization report is developed using Project Online data tables, Resource assignments and capacity.
Resource Utilization percentage is calculated by dividing sum of assignment work by sum of resource capacity.
To achieve similar report for Project (Planner) additional customization is required as resource capacity not available in existing solution tables.
Thanks & Regards,
Ratan Pushp