Hi Jeanine.
The maximum capacity shown in the resource sheet refers to the current day, so if that day is outside the resource's availability range, it will show 0%.
You can check the maximum capacity on any day of the resource's availability range by entering a date within the range in Project > Properties > Project Information > Current Date.
I hope I have helped you.Ignacio Martin