Forum Discussion
FilipeCuango
Apr 04, 2022Tin Contributor
Resource with elapsed days
Hello team . I have a uneasiness. If a 3.66 hour activity (09:00 – 13:00) with a 20-minute break. It has resources (People) that take the break and others don't (equipment), working in full for th...
- Apr 04, 2022Filipe,
Please, allow me to quell you uneasiness.
Create a resource calendar that does not have the 20 minute break for the equipment resource(s). To do that go to the Resource Sheet, select the equipment resource and then select Project > Change Working Time. Eliminate the 20 break period for each day. That will create a custom calendar for that resource but you will not see it listed in the Calendars tab of the Organizer or as a change to the resource Base Calendar. However, when you assign that resource to a task, that resource's daily work content will be the full 4 hours, assuming you did NOT select the option, "Scheduling ignores resource calendars".
Again, if you have separate tasks that use only the equipment resource, do NOT enter duration in days because remember, you day is 3.66666 hours. Enter duration as 4*60 = 240 minutes.
If your equipment also runs even when no labor resources are present (e.g. overnight or on weekends) a different approach is needed.
John
John-project
Apr 04, 2022Silver Contributor
Filipe,
Please, allow me to quell you uneasiness.
Create a resource calendar that does not have the 20 minute break for the equipment resource(s). To do that go to the Resource Sheet, select the equipment resource and then select Project > Change Working Time. Eliminate the 20 break period for each day. That will create a custom calendar for that resource but you will not see it listed in the Calendars tab of the Organizer or as a change to the resource Base Calendar. However, when you assign that resource to a task, that resource's daily work content will be the full 4 hours, assuming you did NOT select the option, "Scheduling ignores resource calendars".
Again, if you have separate tasks that use only the equipment resource, do NOT enter duration in days because remember, you day is 3.66666 hours. Enter duration as 4*60 = 240 minutes.
If your equipment also runs even when no labor resources are present (e.g. overnight or on weekends) a different approach is needed.
John
Please, allow me to quell you uneasiness.
Create a resource calendar that does not have the 20 minute break for the equipment resource(s). To do that go to the Resource Sheet, select the equipment resource and then select Project > Change Working Time. Eliminate the 20 break period for each day. That will create a custom calendar for that resource but you will not see it listed in the Calendars tab of the Organizer or as a change to the resource Base Calendar. However, when you assign that resource to a task, that resource's daily work content will be the full 4 hours, assuming you did NOT select the option, "Scheduling ignores resource calendars".
Again, if you have separate tasks that use only the equipment resource, do NOT enter duration in days because remember, you day is 3.66666 hours. Enter duration as 4*60 = 240 minutes.
If your equipment also runs even when no labor resources are present (e.g. overnight or on weekends) a different approach is needed.
John
- FilipeCuangoApr 05, 2022Tin Contributorit worked perfectly thank you very much again. For your great advice jonh. A big hug. 🙂
- John-projectApr 05, 2022Silver ContributorFilipe,
You're welcome and thanks for the feedback.
John