Forum Discussion
sirsleep29
Sep 09, 2024Brass Contributor
Resource Question
Hello, I put all my separate projects into my schedule with them all being under the main project (have example project included). They have not been inserted but rather built out in the schedule. Be...
Sep 09, 2024
sirsleep29 --
Apply the Resource Usage view. Collapese the task assignments for all of your resources. Right-click in the timephased grid (timesheet-like grid on the right) and select the Remaining Availability field. Zoom the timescale to the desired level of zoom, where Days is the initial default level of zoom. Hope this helps.
Apply the Resource Usage view. Collapese the task assignments for all of your resources. Right-click in the timephased grid (timesheet-like grid on the right) and select the Remaining Availability field. Zoom the timescale to the desired level of zoom, where Days is the initial default level of zoom. Hope this helps.
- sirsleep29Sep 10, 2024Brass Contributor
Hi Dale, thank you for the info. I realized that I never made tasks as part of the test projects and rather kept the at the same level but did make that change (pdf enclosed) so now my next question is when I choose the remaining availability, collapse them down but then open them for a specific person the tasks do show but is there a way to get the test project to show so that we know which project the person has availability for?
- John-projectSep 10, 2024Silver Contributorsirsleep29,
Although not directly available in Project's Resource Usage view, grouped or not, this could be accomplished with an export to Excel using VBA. However, my question is, if a resource has a total availability of 100% and he/she is assigned at 40% on project 1 and 40% on project 2, how would you know which project should get the remaining 20% remaining availability?
John - Sep 10, 2024sirsleep29 --
If you apply the Assignments Keeping Outline Structure group to the Resource Usage view, a negative consequence is that the Remaining Availability information disappears in the timephased grid. So, unfortunately, there is no way to view each project (represented by summary tasks) WITHOUT using the Assignments Keeping Outline Structure grouping. Sorry, but hope this helps.