Forum Discussion
RobertOrnelas
Jan 04, 2024Iron Contributor
Resource pool duplicate resources
I have been using a resource pool with the same master project for months, and everything has been working fine. Maybe I'm mistaken, but I think I remember a dialog popping up that might have said s...
- Jan 07, 2024RobertOrnelas,
First of all, linked structures in Project (i.e. master/subprojects, resource pool/sharer) are prone to corruption. It sounds like something went sideways in your structure. Take a look at the following similar thread to see if it might help.
https://techcommunity.microsoft.com/t5/project/shared-pool-resources-are-shown-separately-in-linked-project/m-p/3052166#M2630
John
RobertOrnelas
Jan 04, 2024Iron Contributor
this could be the message I am thinking of...