Resource leveling doesnt do anything
Good day folks, Hopefully you will be able to help me here - fairly new to MSP. Background - I'm using MSP to manage aircraft heavy maintenance input phases. I have my team set up as work resource...
Ignacio_Martin
Aug 01, 2025Steel Contributor
Hi Richard
Although it's not possible to know what's happening in your project based only on the information you describe, I'm informing you about a situation in which the conflicting resource does not level, assuming this is your case and may be helpful:
If you have two tasks in overallocation with a resource, both Fixed Duration tasks, and you assign more work to the resource on each task than they can complete based on their working time (rersource calendar), Project won't level the task.
Ignacio
Ignacio_Martin
Aug 02, 2025Steel Contributor
P.D. In the previous example, Resource1 has the same calendar as the Project (Estándar).