Forum Discussion
lpf24
Sep 27, 2023Copper Contributor
Resource Allocation Report
I'm using microsoft project online (not project for web). I have a few projects and I need to have a report that gives me an overview of the availability in the near future. In each project I ha...
RodFromm
Oct 02, 2023Steel Contributor
Without going into too much detail, check the duration of the tasks you've assigned resources and ensure the Finish date is correct? For example, if the task defaulted to a 1 day duration, when it should be 30 or 60 days, you will not see any future work in MSP Online or the Power BI reports.