Forum Discussion
Rescheduling unachieved task
How exactly are you updating? The Update Project feature allows you to reschedule uncompleted work after a date you select. Is that not working for you?
A more detailed explanation of your issue with some screen shots would help us help you.
John
Hi John,
To simplify I only kept 1 task / 1 resources and cleaned the entire project file:
AUTOMATIC SCHEDULE/FIXED WORK/NO CONSTRAINT DATE
WORK = 100 md / % COMPLETED 90 % ==> remaining work 10 md
Task assigned to one single resource 100% available
I UPDATED THE ENTIRE PROJECT asking to reschedule the remaining work after August 7th
Result is not correct : the task finish date is set to October 27th !
Looking at the resource allocation : +/- 70 md assigned for a remaining work of 10 md !
I do not know where I missed something ...
Thanks for your support
Philippe