Forum Discussion
vergilangleos
Jul 06, 2024Copper Contributor
Reschdule out of order task
Hello everyone Recently, I encountered a problem in my rescheduling, I have activities which started earlier than their predecessors, and after rescheduling they reschedule as retained logic, when i...
Ignacio_Martin
Jul 11, 2024Iron Contributor
If I understand you correctly, you must first remove the link with the predecessor, set the option: Schedule > Split in-progress tasks > Deselected and Advanced > Move end of completed parts after status date back to status date > Deselected, and then select task and select option Task > Tasks > Move > Incomplete Parts to Status Date
Note: Enter the %completed first and then the actual start date.
Ignacio