Forum Discussion
vergilangleos
Jul 06, 2024Copper Contributor
Reschdule out of order task
Hello everyone Recently, I encountered a problem in my rescheduling, I have activities which started earlier than their predecessors, and after rescheduling they reschedule as retained logic, when i...
vergilangleos
Jul 09, 2024Copper Contributor
hello again
my baseline is something like this:baseline
when i reschedule with split task is on its like this:
and after disabling split task from option>scheduling its like this:
as you can see it has scheduling error and remaining work of task B is now before my new date after rescheduling. what i want is when i reschedule a task like this the remaining work start in my new status date while ignoring predecessor
John-project
Jul 09, 2024Silver Contributor
vergilangleos,
Obviously you are not on the Gregorian calendar since your year is 1446. That aside, I'm having trouble understanding exactly what you did when you "rescheduled with split task" to produce the second screen shot. And then, what steps did you perform for the third screen shot.
Generally, if you start a task early, as seems to be the case in screen shot #2, and split task is activated, then remaining work will be re-scheduled after the status date, assuming that option is set up in Project options. However, if split task is not enabled, then Project will not re-schedule remaining work after the status date. For reference, once a task's actual start date is set any predecessors are null and void (i.e. they no longer matter because the actual start takes precedence).
John
Obviously you are not on the Gregorian calendar since your year is 1446. That aside, I'm having trouble understanding exactly what you did when you "rescheduled with split task" to produce the second screen shot. And then, what steps did you perform for the third screen shot.
Generally, if you start a task early, as seems to be the case in screen shot #2, and split task is activated, then remaining work will be re-scheduled after the status date, assuming that option is set up in Project options. However, if split task is not enabled, then Project will not re-schedule remaining work after the status date. For reference, once a task's actual start date is set any predecessors are null and void (i.e. they no longer matter because the actual start takes precedence).
John